SANG application procedure
Steps | Strategic SANG Procedure | Third Party SANG procedure |
---|---|---|
STEP ONE | Contact the Council to establish there is sufficient capacity for the Strategic SANG to mitigate the proposed development (planning.policy@RBWM.gov.uk) |
Contact the Private SANG owner / manager to secure formal / legal agreement for SANG mitigation |
STEP TWO | Submit planning application with confirmation of Strategic SANG capacity | Submit application with a binding Third Party SANG agreement to demonstrate SANG has been secured |
STEP THREE | Enter into a s106 Agreement with the Royal Borough to secure SANG and SAMM payment upon commencement of the development | Enter into a s106 Agreement with the Royal Borough, drafted on the basis that an agreement has already been entered into with the Third Party SANG owner and the SANG contribution paid direct to that party (evidence of this Third Party agreement will be annexed to the s106 agreement with the Council) and securing SAMM contributions upon commencement of the development, paid direct to the Council. |
STEP FOUR | Planning application decision issued. | Planning application decision issued |
STEP FIVE | If planning permission is granted, implement in accordance with the s106 agreement and planning conditions attached to the decision notice | If planning permission is granted, implement in accordance with the s106 agreement and planning conditions attached to the decision notice |
The submission of a request for Pre-application advice is recommended to establish the process and requirements prior to the submission of a formal planning application Requesting pre-application advice.